Q5 of 47 Page 174

A works twice as fast as B. If both of them can together finish a piece of work in 12 days. then B alone can do it in

Work done by A in one day: 2x


Work done by B in one day: x


Number of days taken by A and B to do the work together: 12 days


Work done by A and B together in one day:


= 2x + x


= 3x


X =


Here X is Work done by B in one day


B alone will take 36 days to complete the work.

More from this chapter

All 47 →
3

A can do a job in 16 days and B can do the same job in 12 days. With the help of C. they can finish the job in 6 days only. Then, C alone can finish it in

4

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

6

A alone can finish a piece of work in 10 days which B alone can do in 15 days. If they work

together and finish it, then out of total wages of Rs.3000. A will get

7

The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio

Questions · 47
13. Time and Work
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 1 2 3 4 5 6 7 8 9 10 11
Back to chapter
ADVERTISEMENT
About Contact Privacy Terms
Philoid · 2026
  • Home
  • Search
  • Browse
  • Quiz
  • Saved