A manufacturer produces two type of steel trunks. He has two machines A and B. For completing, the first types of the trunk requires 3 hours on machine A and 3 hours on machine B, whereas the second type of the trunk requires 3 hours on machine A and 2 hours on machine B . Machines A and B can work at most for 18 hours and 15 hours per day respectively. He earns a profit of Rs 30 and Rs 25 per trunk of the first type and the second type respectively. How many trunks of each type must
he make each day to make maximum profit?

Let x trunks of first type and y trunks of second type were manufactured. Number of trunks cannot be negative.


Therefore, x, y 0


According to the question, the given information can be tabulated as



Therefore, the constraints are,


3x + 3y 18


3x + 2y 15.


He earns a profit of Rs 30 and Rs 25 per trunk of the first type and the second type respectively. Therefore, profit gained by him from x trunks of first type and y trunks of second type is Rs 30x and Rs 25y respectively.


Total profit Z = 30x + 25y which is to be maximized.


Thus, the mathematical formulation of the given LPP is


Max Z = 30x + 25y


Subject to


3x + 3y 18


3x + 2y 15


x, y 0


Region 3x + 3y 18: line 3x + 3y = 18 meets axes at A(6,0), B(0,6) respectively. Region containing origin represents the solution of the inequation 3x + 3y 18 as (0,0) satisfies 3x + 3y 18.


Region 3x + 2y 15: line 3x + 2y = 15 meets axes at C(5,0), D(0,) respectively. Region containing origin represents the solution of the inequation 3x + 2y 15 as (0,0) satisfies 3x + 2y 15.


Region x,y 0: it represents first quadrant.


20.jpg


The corner points are O(0,0), B(0,6), E(3,3), and C(5,0).


The values of Z at these corner points are as follows:



The maximum value of Z is 165 which is attained at E(3,3).


Thus, the maximum profit is of Rs 165 obtained when 3 units of each type of trunk is manufactured.

More from this chapter

All 20 →
12

A factory manufactures two types of screws, A and B, each type requiring the use of two machines - an automatic and a hand - operated. It takes 4 minute on the automatic and 6 minutes on the hand - operated machines to manufacture a package of screws ‘A’, while it takes 6 minutes on the automatic and 3 minutes on the hand - operated machine to manufacture a package of screws ‘B’. Each machine is available for at most 4 hours on any day. The manufacturer can sell a package of screws ‘A’ at a profit of 70 P and screws ‘B’ at a profit of ₹ 1. Assuming that he can sell all the screws he can manufacture, how many packages of each type should the factory owner produce in a day in order to maximize his profit? Determine the maximum profit.

13

A manufacturer makes two types A and B of tea - cups. Three machines are needed for the manufacture and the time in minutes required for each cup on the machines is given below :


Each machine is available for a maximum of 6 hours per day. If the profit on each cup A is 75 paise and that on each cup B is 50 paise, show that 15 tea - cups of type A and 30 of type B should be manufactured in a day to get the maximum profit.

15

A gardener has a supply of fertilizer of type I which consists of 10% nitrogen and 6% phosphoric acid and type II fertilizer which consists of 5% nitrogen and 10% phosphoric acid. After testing the soil conditions, he finds that he needs at least 14 kg of nitrogen and 14 kg of phosphoric acid for his crop. If the type I fertilizer costs 60 paise per kg and type II fertilizer costs 40 paise per kg, determine how many kilograms of each fertilizer should be used, so that nutrient requirements are met at a minimum cost. What is the minimum cost?

16

An oil company has two depots A and B with capacities of 7000 L and 4000 L respectively. The company is to supply oil to three petrol pumps, D, E and F whose requirements are 4500L, 3000L and 3500L respectively. The distances (in km) between the depots and the petrol pumps is given in the following table:


Assuming that the transportation cost of 10 liters of oil is Re 1 per km, how should the delivery be scheduled in order that the transportation cost is minimum? What is the minimum cost?