Twelve carpenters working 10 hours a day complete a furniture work in 18 days. How long would it take for 15 carpenters working for 6 hours per day to complete the same piece of work?

Let x be the no. of days to be found out
Step :1
Considering the carpenter and the no. of days
The multiplying factor = ![]()
Step :2
Considering the no. of hours in a day and the no. of days
The multiplying factor = ![]()
x =
×
× 18
x = 24 days