If 2,400 sq.m. of land can be tilled by 12 workers in 10 days, how many workers are needed to till 5,400 sq.m. of land in 18 days?

Considering the Area of land and no. of workers
The multiplying factors ![]()
Considering the No. of days and no. of workers
The multiplying factors ![]()
So, the No. of compositors required
x =
×
× 12
x = 15
Couldn't generate an explanation.
Generated by AI. May contain inaccuracies — always verify with your textbook.