If 10 men working 7 hrs a day dig a trench 147 m long; how many men working 8 hrs a day will dig a trench 160 m long?

Working 7 hours a day 147 m long trench can be dug by 10 men.


Working 1 hour a day 147 m long trench can be dug by


= 10 x 7 = 70


Working 1 hour a day 1 m long trench can be dug by


Working 8 hours a day 1 m long trench can be dug by


Working 8 hours a day 160 m long trench can be dug by


= 9.523


As the men cannot be in decimal or fraction, so, rounding off we get 10 men.


So, it would take 10 men working 8hr a day to dug 160m trench.